This project involved replacing the existing synthetic turf fields and performing other ADA compliance work at American Canyon High School, Napa High School, Vintage High School, Redwood Middle School, Silverado Middle School and Memorial Stadium. Tasks included removing the existing carpet, shock pad and fabric; repairing or replacing sub drainage; re-grading the field; installing new geotextile fabric; reinstalling the stored shock pad and installing new synthetic turf. A total of approximately 497,542 square feet of turf was replaced.
Owner: Napa Valley Unified School District
Turf Cost: $5,449,980
ADA Cost: $249,633
Architect: Verde Design
Contractor: Valley Precision Grading, AstroTurf