Portfolio > East Side UNION High School District

R

Bond ProgramS

Measure E and Measure N

R

DELIVERY METHODS

DBB, LLB, DB

R

MANAGEMENT DURATION

2011-present

R

Program Elements

Modernization, New Construction, Roofing, Paint, Field

PROJECTS

The projects listed below are some but not all of the projects that we have managed for ESUHSD:

  • Independence High School
    • Building F modernization
    • Buildings G&N modernization
    • Building B modernization
    • Wayfinding project
  • WC Overfelt High School
    • Music, Art and Admin Building
    • Building J modernization
  • Andrew Hill High School
    • Courtyard/hardscape modernization
  • Piedmont High School
    • Building D1 and D2 (new science)
    • Campus improvements
  • Evergreen Valley High School
    • Science labs and prep rooms

Services

  • Project management
  • Project scheduling
  • Coordination with design team
  • Cost estimating
  • Value engineering coordination
  • Constructability review
  • Pre-construction oversight
  • DSA coordination
  • Inspector of record coordination
  • Bid coordination
  • Temporary housing and move coordination
  • Correspondence with public utility providers
  • Correspondence with regulatory agencies
  • Attend School Board meetings
  • Review of change order requests